TEMA SHELL & TUBE HEAT EXCHANGERS
EPC-READY DELIVERY

Practical guidance for EPC teams procuring shell-and-tube heat exchangers: freeze the datasheet early, confirm TEMA construction intent, align inspection hold points with the master schedule, and release shipment only when the vendor data book is complete.

WHAT EPC TEAMS USUALLY CARE ABOUT

Four priorities that drive successful heat exchanger procurement.

  • Battery limits definition — clear vendor scope vs. site scope boundary, agreed at contract award
  • Predictable inspection & testing — ITP with clear hold points and witness points aligned to master schedule
  • Document quality & completeness — the data book is as critical as the hardware
  • Shipment readiness — preservation adequate for transport duration and storage conditions

DELIVERY TRACK RECORD

  • 100% FAT success rate across recent deliveries
  • Zero document rejections on last 12 projects
  • BV / TÜV / Lloyds 3rd party witness coordination
  • 48 hr technical proposal turnaround

SCOPE BOUNDARY TABLE

Vendor vs. EPC responsibility split — defined at contract award.

Workstream Typically Included (Vendor) Typically By EPC / Site What Vendor Needs From EPC Early
Datasheet / Basis Review + clarification Issue final process datasheet Duty, fouling, ΔP, design P/T, materials, corrosion allowance
Thermal & Mechanical Design Sizing summary + mechanical details Approve key assumptions, interfaces Process guarantees, operating cases, design codes, nozzle loads
Drawings GA, nozzle schedule, bundle, supports Review/approve; coordinate piping/steel Tie-in locations, plot constraints, access needs
Fabrication Shell/channel/bundle per drawings Approval turnaround, hold point notice windows
Materials & Traceability Pressure parts MTR + heat number docs Define documentation level (MDR/VDRL) Cert type (EN 10204 3.1/3.2), TPI requirements
Inspection & NDE NDE execution per ITP (RT/UT/PT/MT), weld map Witness/hold as required ITP hold points, acceptance criteria, witness plan
Pressure Testing Hydrotest/leak test per contract Witness/hold as required Test configuration, medium restrictions, safety
Preservation & Packing Flange protection, desiccant, rust prevention, export packing Site receiving + storage Storage duration, shipping mode/route constraints
Site Integration Foundations, rigging, external piping, insulation Site constraints, lifting limits, installation schedule
Turnover Documents Vendor Data Book, as-builts, test evidence Document control + final turnover MDR/VDRL format, naming convention, transmittal rules

HOW TO SPECIFY WITHOUT TBDs

Minimum EPC-ready datasheet elements.

  • Duty + operating cases (normal, max, min, start-up, upset if relevant)
  • Fouling factors (both sides) and expected cleaning philosophy
  • Allowable pressure drop ΔP (both sides) and pump/compressor constraints
  • Design pressure/temperature and corrosion allowance assumptions
  • Materials (shell/channel/tubesheets/tubes) + any PMI requirement
  • Nozzle loads / interface constraints
  • Maintenance requirement (bundle pull access needed or not)

TEMA CONSTRUCTION TYPES

Selecting the right configuration for your service.

Fixed Tubesheet

Pros: Simpler, often cost-effective.
Watch-outs: Differential thermal expansion can be a design driver; shell-side cleaning more constrained.

Floating Head (Bundle Pull-Friendly)

Pros: Easier mechanical access for cleaning/inspection; preferred when fouling expected.
Watch-outs: More parts, increased complexity, usually higher cost/lead time.

U-Tube

Pros: Handles thermal expansion well.
Watch-outs: Mechanical cleaning inside U-bends harder; tube replacement more involved.

Note: TEMA standards emphasize using a single consistent unit system (US Customary or SI) across design and fabrication.

ITP MILESTONES

Seven critical tracking points for EPC inspection.

# Milestone Key Activity
1 Materials Received Traceability established — MTRs linked to heat numbers
2 Fit-up / Dimensional Nozzle orientation, support geometry verification
3 Tube Bundle Build Tube-to-tubesheet joint — critical hold point
4 NDE Complete Reports compiled and linked to weld map
5 Hydrotest / Leak Test Test record signed by all parties
6 Final Inspection Preservation + packing confirmation
7 Data Book Released Fully released — not "almost done"

FAT / SHOP ACCEPTANCE

What EPC teams need to verify before release.

Heat exchangers typically don't undergo formal FAT like control systems, but EPC teams need to confirm:

  • Dimensional conformity (interfaces critical to project)
  • Traceability evidence (MTRs, heat numbers)
  • NDE completion and acceptance
  • Hydrotest/leak test record
  • Preservation/packing confirmation

VENDOR DATA BOOK CONTENTS

Clean EPC turnover — example directory.

# Document
1 Final datasheet / spec sheet
2 Thermal design summary (assumptions clearly stated)
3 Mechanical design summary (construction intent, key thicknesses)
4 GA + nozzle schedule + bundle drawing (as-built)
5 MTRs / traceability summary (per contract)
6 NDE reports (linked to weld map)
7 Hydrotest / leak test report
8 Preservation + packing record (photos recommended)
9 Final document register + release-to-ship statement

SHIPPING & PRESERVATION

Key specifications to include in PO.

  • Flange face protection — don't rely on plastic caps alone for long storage
  • Rust prevention + desiccant strategy (especially for carbon steel components)
  • Nozzle covers clearly tagged (temporary vs. permanent distinction)
  • Bundle pull protection (if pullable) and lifting instructions included
  • Export packing aligned to shipping route (salt air, humidity, vibration, handling points)

DOWNLOADABLE TEMPLATES

EPC-ready checklists and tracking documents for your shell-and-tube heat exchanger project.

Delivery Milestones Map

7-stage milestone tracker from contract award to data book release. Align with your master schedule.

Download PDF

FAT / Inspection Checklist

Pre-release verification checklist covering dimensional, traceability, NDE, pressure test, and packing.

Download PDF

Vendor Data Book Index

Standard VDB directory structure for clean EPC turnover. 9-section format per industry best practice.

Download PDF

RELATED PAGES

Explore Lmart's heat exchanger capabilities and standards resources.

Heat Exchangers (TEMA)

Full product overview — shell and tube configurations, materials, and specifications.

Titanium Heat Exchangers

110+ Ti units delivered to the customer and TGE Marine.

TEMA Standards Guide

TEMA units, datasheet expectations, and class R/B/C selection criteria.

ASME U-Stamp Guide

ASME Section VIII Division 1 requirements and U-Stamp certification process.

REFERENCES

Frequently Asked Questions

Which TEMA construction is easiest to maintain (bundle pull vs. not)?

If fouling is expected and mechanical cleaning is predictable, a bundle pull-friendly construction (floating head) is often preferable. If fouling is minimal and access constraints dominate, a simpler fixed tubesheet configuration may suffice. The best choice depends on cleaning philosophy and site access.

What should be in the TEMA datasheet to avoid redesign loops?

Minimum elements include duty + operating cases, fouling factors, allowable ΔP, design P/T, materials + corrosion allowance, and nozzle/interface constraints. Most redesign loops occur when these inputs are incomplete or change after IFA drawings.

How do you handle units (US customary vs. SI) consistently?

Select one unit system for design/fabrication and maintain consistency across datasheets, drawings, and calculations. TEMA standards note that US Customary and SI are both available, but a single system of units should apply to all design and fabrication aspects, with limited exceptions.

Can Lmart coordinate ASME & PED 3rd party witnesses?

Yes. We coordinate with Bureau Veritas, TÜV, and Lloyds for both ASME Authorized Inspection and PED Notified Body (NoBo) requirements. Our ITP workflow provides clear notification windows for EPCs to arrive for hold-point witness.

What is the typical lead time for an EPC heat exchanger order?

Standard TEMA units: 14–18 weeks from AFC drawings. Complex units with exotic materials (titanium, Hastelloy, duplex) or PED Module H certification: 18–24 weeks. Lead time is confirmed at contract award and tracked via our digital milestone dashboard.

How is the Vendor Data Book (VDB) delivered?

The VDB is compiled digitally throughout production and delivered as a structured PDF package within 48 hours of final inspection. Contents include: MDR compliance matrix, all MTRs (EN 10204 3.1/3.2), WPS/PQR, NDE reports, hydro-test records, dimensional reports, and class certificates.