Blog / Technical Guides

How to Select an Industrial Refrigeration Unit in 2026: Evaporating Temperature, Refrigerant and Compressor in Three Steps

Key Takeaways

  • Selection has a fixed order: evaporating temperature → refrigerant → compressor type. Reverse it and every downstream number — shaft power, stage count, vessel design pressure, budget — is built on a guess.
  • Evaporating temperature = process outlet temperature − approach (4–8 K). Every 1 °C you drop it costs roughly 2–3 % more compressor power for the life of the plant. Put your design margin in capacity (~10 %), never in temperature.
  • Refrigerant choice is now a compliance decision, not only a thermodynamic one. China's full-lifecycle refrigerant management rules took effect in March 2026, and high-GWP fluids such as R507A (GWP ≈ 4,000) are being squeezed. Ammonia (GWP 0) and propylene (GWP ≈ 2) are increasingly the default for new petrochemical duties.
  • Screw compressor packages own the middle ground — a few hundred kW up to roughly 13,000 kW, swinging loads, low evaporating temperatures — because slide-valve control is stepless from 10 % to 100 %.
  • Bids are only comparable if the datasheet is complete. Fix evaporating temperature, condensing conditions and secondary-fluid flow before you compare prices, and always ask for shaft power at 50 %, 75 % and 100 % load.

Most industrial refrigeration enquiries that reach our desk open the same way: "We need a 1,000 kW screw chiller package. Please quote." One number, one machine type, and the single parameter that actually determines the design is missing — the evaporating temperature.

A 1,000 kW duty at −10 °C and a 1,000 kW duty at −40 °C are not variants of the same package. They are different machines: different pressure ratio, motor power differing by more than a factor of two, possibly single-stage versus two-stage, different refrigerant, different vessel design pressure, and a delivered price that can differ by well over 50 %. Quoting the first without knowing the second is guesswork dressed up as a proposal.

This guide sets out the selection sequence we use when supporting design institutes and EPC contractors on process refrigeration duties: evaporating temperature first, refrigerant second, compressor type third. It is a methodology piece rather than a vendor comparison — if you have already settled the duty and want to know who builds these packages in China, that ground is covered separately in our 2026 buyer's guide to industrial refrigeration package manufacturers.

Skid-mounted industrial refrigeration package for a −40 °C ethane storage duty
A skid-mounted refrigeration package for a −40 °C ethane tank-farm duty. Evaporating temperature — not nominal capacity — drove every design decision on this unit.

Why the Order of Selection Matters

The three variables are not independent. Evaporating temperature sets the pressure ratio the cycle must deliver, and pressure ratio narrows the refrigerant field. Refrigerant properties then set suction volume flow, discharge temperature and the number of compression stages, which in turn narrows the compressor type. Work in that direction and each decision closes off options cleanly. Work backwards — picking a machine first — and you spend the rest of the project bending the process to suit hardware that was chosen before anyone knew what the process needed.

This matters commercially as well as technically. In tenders where the datasheet leaves evaporating temperature open, bidders fill the gap with their own assumptions. The resulting quotations look comparable and are not. We routinely see two bids separated by 15–20 % on price where one supplier assumed −20 °C and the other −25 °C — a difference of roughly a stage of compression, not of commercial sharpness.

Step 1: Fix the Evaporating Temperature

The rule is straightforward:

Evaporating temperature = outlet temperature of the cooled medium − heat transfer approach

The approach normally sits between 4 and 8 K. Flooded evaporators, with their higher shell-side coefficients, work comfortably at the tight end (4–5 K); direct-expansion evaporators need the wider end (6–8 K). If a process demands glycol solution leaving at −15 °C through a flooded evaporator, the evaporating temperature lands around −20 °C.

The 2–3 % rule and where margin belongs

Here is the number worth writing on the datasheet cover: every 1 °C reduction in evaporating temperature raises compressor power consumption by roughly 2–3 %. That penalty is permanent. It is paid every operating hour for the twenty-year life of the plant.

Which is why the most expensive habit in refrigeration specification is the "safety margin" applied to temperature. A process engineer needs −15 °C, writes −20 °C on the datasheet to feel comfortable, and quietly commits the owner to 10–15 % higher energy cost forever. Margin belongs in capacity — around 10 % is normal and defensible — and in fouling allowance on the exchangers. It does not belong in temperature.

The counter-argument is usually heat exchanger cost: widening the approach by 2 K shrinks the surface area and the capital cost of the evaporator. Run the numbers over the operating life and the electricity bill wins almost every time on a continuously running process duty. It is a conversation worth having with your package supplier before the datasheet is frozen, not after.

Step 2: Match the Refrigerant to the Temperature Band

Once evaporating temperature is fixed, the refrigerant field narrows sharply. Each band has mature, well-proven options:

Evaporating temperature Typical duty Common refrigerants System configuration
0 to −10 °C Chilled water, process cooling R134a, ammonia (R717) Single stage
−15 to −25 °C Brine / glycol secondary loops Ammonia, R507A, propylene (R1270) Single stage with economiser
−30 to −45 °C Tank-farm direct cooling, low-temperature process Propylene, two-stage ammonia Two-stage, or single stage with economiser
Below −60 °C Ethylene liquefaction Ethylene cascade Cascade system

The regulatory column you now have to add

Since March 2026, China's Ministry of Ecology and Environment has applied full-lifecycle registration to refrigerants — production, sale, use, recovery and destruction each logged, with direct venting prohibited and dedicated provisions for ammonia and CO2 systems. The practical effect on new projects is that GWP has become a selection column alongside capacity and efficiency.

The spread is wide. R507A carries a GWP close to 4,000 and R134a around 1,430; both sit in the tightening band. Ammonia has a GWP of zero and propylene approximately 2. Ammonia still accounts for roughly 41 % of the global industrial refrigerant load, and petrochemical sites have a structural advantage with propylene: the plant already produces it, so make-up charge becomes an internal logistics question rather than a procurement one. Propylene's share of new-build process refrigeration duties has risen noticeably over the last few years for exactly this reason.

None of this makes fluorinated refrigerants unusable. Installed plant continues to run, and new installations are not banned outright. But specifying a high-GWP fluid on a twenty-year asset in 2026 is a decision to hand a retrofit project to your successor around 2031. For long-life process duties, the natural refrigerants deserve the first look.

Direct expansion or a secondary loop?

The refrigerant decision carries a system-architecture decision with it. Direct cooling is more efficient — you avoid a whole secondary circulation loop and its pumping power and temperature penalty — and suits duties where the cold users are concentrated. A secondary loop (glycol or brine) costs efficiency but confines the refrigerant charge to the compressor house, keeps it out of the process area entirely, and simplifies hazard management. On ammonia duties in congested plants, that containment argument frequently decides the layout on its own.

Step 3: Choose the Compressor Type

With temperature and refrigerant settled, compressor selection is largely constrained already. The three mainstream machine types divide up as follows:

Criterion Screw Reciprocating Centrifugal
Capacity per machine ≈ 200–13,000 kW Generally below 500 kW Above 2,000 kW
Pressure-ratio capability Strong; with economiser reaches deep-cooling duties Strong Weaker; surge risk at low load
Capacity control Stepless slide valve, 10–100 % Cylinder unloading, stepped Inlet guide vanes, limited below ~40 %
Wear parts and maintenance Few moving parts, long overhaul interval Valve plates, piston rings replaced frequently High precision, demanding maintenance regime
Typical position Mainstream for petrochemical refrigeration Small capacity, unusual pressure ratios Large, stable base load

Condensed to three sentences: where capacity is small and the pressure ratio awkward, reciprocating machines still have a place; where capacity is very large and load genuinely flat, centrifugal efficiency wins; and the broad middle — a few hundred kW to five figures, fluctuating load, low evaporating temperature — belongs to the screw compressor.

That middle band describes most petrochemical process refrigeration, because petrochemical load is rarely flat. Start-up, grade changes, seasonal ambient swing and turndown all move the cold demand around, and this is precisely where stepless slide-valve control earns its keep. A centrifugal machine held at 35 % load is a different proposition from a screw package at 35 % load. The largest single screw package we have integrated was a twin-screw unit for a styrene plant at 10,863 kW — a duty that a decade ago would have been assumed to be centrifugal territory by default.

One point of transparency about scope: Lmart integrates screw compressor packages — compressor bare shafts are purchased from established compressor manufacturers. What we design and build in house is the code-compliant pressure envelope around them: pressure vessels, shell-and-tube heat exchangers, separators and receivers, oil systems, piping and the complete skid. The reciprocating and centrifugal comparison above is drawn from published industry data and from packages we have supplied alongside, and is offered as orientation rather than as a claim of manufacturing scope.

Two Worked Examples, Two Different Answers

Case 1 — −15 °C class brine package

A PMMA unit at a domestic chemical producer required low-temperature brine. The delivered configuration: three brine chiller packages, 980 kW each, R134a, glycol solution as the secondary fluid.

At this temperature band the pressure ratio is mild, so single-stage screw compression on R134a keeps the system simple. Three units in parallel give operational redundancy and let the plant follow load by taking machines offline rather than running everything at deep turndown. The secondary loop concentrates the refrigerant charge in the machine room, so no refrigerant reaches the process side — a straightforward safety case for the operator.

Case 2 — −38 °C ammonia direct-cooling package

A Rectisol (low-temperature methanol wash) unit at a domestic new-materials producer specified −38 °C evaporating temperature, 5,600 kW per unit, four units, ammonia.

At −38 °C the single-stage pressure ratio is already stretched, so the packages use economiser vapour injection to hold isentropic efficiency and control discharge temperature. Ammonia was chosen partly on efficiency in this band and partly on compliance: with GWP zero, the owner side-steps the phase-down question entirely. At 5,600 kW per machine only screw or centrifugal machines are candidates, and because the load swings, screw won.

Put the two side by side. The evaporating temperatures differ by just over 20 °C — and the refrigerant, the system architecture, the stage configuration and the whole safety design differ completely. That is the argument for the sequence in one picture.

Duties get more layered than this, too. One chemical plant's XDI unit needed 1,828 kW at −25 °C and 86 kW at −45 °C simultaneously. Rather than forcing a single dual-temperature system, the answer was to split the temperature levels and give the small deep-cooling duty its own dedicated machine — less power, less complexity, easier operation.

The Datasheet Checklist That Makes Bids Comparable

Selection discipline is worth little if the enquiry documents don't carry it through to the bidders. At minimum, a refrigeration package datasheet should state:

  • Refrigeration capacity at the rated point, and the design margin basis
  • Evaporating temperature — or the secondary fluid inlet/outlet temperatures and flow rate, so bidders derive the same number
  • Condensing side conditions — cooling water supply temperature and available flow, or ambient design temperature for air-cooled duty
  • Refrigerant, including any owner restriction on GWP or on ammonia in the process area
  • Load range and expected operating profile — how many hours at what percentage load
  • Shaft power at 50 %, 75 % and 100 % load as a required deliverable in the bid
  • Electrical supply voltage and frequency, and the hazardous-area classification
  • Design codes and third-party requirements for the pressure envelope — ASME BPVC Section VIII Div.1, PED 2014/68/EU, GB/T 150, and classification society involvement where the package goes offshore or on board
  • Interface and footprint constraints — skid envelope, shipping limits, tie-in points, control system architecture

Miss any one of these and the bids you receive are not a like-for-like set.

Three Traps We See Repeatedly

Trap 1 — padding the evaporating temperature. The process needs −15 °C, the datasheet says −20 °C, and the owner pays 10–15 % extra on power for the life of the plant. Put margin on capacity instead.

Trap 2 — comparing prices without normalising the duty point. A RMB 200,000 gap between bids often turns out to be one supplier quoting −20 °C and another −25 °C. Normalise the datasheet before opening commercial envelopes, or the tender evaluation is measuring assumptions rather than suppliers.

Trap 3 — evaluating on full-load COP alone. If the plant spends 70 % of its hours at 60 % load, full-load COP is close to irrelevant. Ask for the part-load curve, and write the guaranteed part-load shaft power figures into the technical agreement rather than leaving them in the sales presentation.

Where an Equipment Supplier Fits In

Suzhou Lmart Energy Equipment has supplied more than 130 industrial refrigeration units since 2016, across R134a, R507A, ammonia, propylene and ethylene, with evaporating temperatures from 0 °C down to cascade duties below −60 °C. Our scope is screw compressor package integration and skid-mounted systems, built around pressure vessels and shell-and-tube heat exchangers manufactured in our own workshops, with design, fabrication, assembly and testing on one site.

We are the equipment supplier on these projects, not the process designer — the duty belongs to the licensor, the design institute and the owner. What we can usefully contribute at the specification stage is a reality check: whether the evaporating temperature and approach are consistent, whether the refrigerant suits the band and the site's compliance posture, and whether a comparable configuration already exists in our delivered project list. That conversation costs a week at the front end and routinely saves several rounds of technical clarification after bids are in.

If you have a refrigeration datasheet in preparation or out for tender, send it over and we will review the parameters against comparable delivered projects and come back with a technical proposal and budget pricing.


Lmart holds ASME U-Stamp, PED/CE, ISO 9001 plus CCS (Type & Works Approval) and works approval from DNV, LR, BV, NK & RINA (KGS for Korea).

103-mu campus in Zhangjiagang · 38,000 m² workshop · 300+ staff · 15,000 T/year capacity

Last reviewed: 16 July 2026 · Technical accuracy verified by Lmart Engineering Dept.

Frequently Asked Questions

Is evaporating temperature the same as the secondary fluid outlet temperature?

No. Evaporating temperature equals the secondary fluid outlet temperature minus the heat transfer approach, normally 4–8 K. A process requiring brine at −15 °C typically corresponds to an evaporating temperature near −20 °C. Both figures should appear on the datasheet so bidders cannot substitute their own assumption.

Can we still buy an R507A package after the 2026 refrigerant rules?

Installed plant may continue operating and new installations are not prohibited outright. However, R507A carries a GWP close to 4,000 and sits squarely in the phase-down path. For assets with a twenty-year horizon we recommend evaluating ammonia or propylene first, and treating any high-GWP selection as a decision that carries a probable future retrofit cost.

At what temperature does two-stage compression become necessary?

The practical boundary sits around −35 °C. Single-stage compression with an economiser can reach roughly −40 °C on a screw package. Below that, or where energy consumption is a dominant evaluation criterion, two-stage or cascade arrangements are usually more economic. The exact crossover depends on pressure ratio and refrigerant properties.

What is the largest capacity available from a single screw package?

Twin-screw packages reach the 13,000 kW class per machine. The largest we have integrated is a 10,863 kW unit for a styrene plant. Above that range, and where load is genuinely stable, centrifugal machines usually offer better efficiency.

Direct cooling or a secondary (glycol/brine) loop — how do we decide?

Direct cooling is more efficient and avoids a whole secondary circulation system, which suits duties where the cold users are concentrated. A secondary loop suits distributed cold users, or plants that do not want refrigerant present on the process side; it costs some efficiency but confines the charge to the machine room and simplifies hazard management — often decisive on ammonia duties.

Does Lmart manufacture the compressors?

No. Lmart integrates screw compressor packages using bare-shaft compressors purchased from established compressor manufacturers. What we manufacture in house is the pressure-bearing equipment and the package itself — pressure vessels, shell-and-tube heat exchangers, separators and receivers, oil systems, piping and skid, with design, fabrication, assembly and testing on one site under ASME U-Stamp, PED 2014/68/EU, ISO 9001 and CCS approval.

You May Also Like

Ready to Discuss Your Project?

Our engineering team delivers technical proposals with GA drawings and budget pricing within 48 hours. 300+ staff, ASME U-Stamp · PED/CE · CCS + DNV/LR/BV/NK/RINA, equipment exported to 50+ countries.

Contact Our Engineering Team


Leave a Comment