The Supplier Factory Audit, Rewritten for 2026: 25 Checks Worth Running
Key Takeaways
- CBAM's definitive period began 1 January 2026, and CSDDD / LkSG pushed ESG due diligence onto the supplier tier. The audit form gained a whole block.
- Set the audit tier before the depth: a qualification audit is 1–2 days, a project audit half a day scoped to your material and code, a witness audit one operation.
- The highest-yield line is welding procedure coverage — and it only works if you bring your own drawing and ask them to find the matching PQR.
- Judge record systems by retrieval speed, not by whether records exist. Ask for the RT film of one weld on a unit shipped three months ago and time the answer.
Why the audit form got longer
On 1 January 2026 the EU's Carbon Border Adjustment Mechanism entered its definitive period. From that date an EU importer of steel-based equipment is no longer just filing a report: it has to obtain third-party verified embedded-emissions data from the works that actually made the goods, with the first annual declaration due 30 September 2027 (source: European Commission, Taxation and Customs Union, 2026). Around the same time CSDDD, CSRD and the German Supply Chain Act (LkSG) pushed ESG due diligence one tier further down, onto the supplier itself.
For anybody buying pressure vessels, shell-and-tube heat exchangers or process skids out of Asia, the consequence is concrete: the factory audit form got longer. The procurement manager who used to walk a shop looking at welding, NDE and quality records now walks the same shop with an extra column on the sheet.
A word on where this is written from. We are on the receiving end of these audits. Our works in Suzhou has been audited, visited or third-party inspected by EPCs and end users including GS E&C, Air Products, Air Liquide Korea and TGE. We are an equipment supplier, not the EPC, not the licensor, not the auditor. Having been on the other side of the table repeatedly is what makes it possible to say which lines on the form separate a genuine audit from a factory tour with a lunch.
First: decide what level of audit this is

Before booking the flight, put the audit in a box. There are broadly three levels, and they demand completely different amounts of time.
| Audit level | Trigger | Depth | Duration |
|---|---|---|---|
| Qualification audit | New supplier, entry to the approved vendor list | System and capability, full sweep | 1–2 days |
| Project audit | Before placing a significant order | Focused on this project's material, code and duty | Half a day to 1 day |
| Witness / surveillance | Hold and Witness points during production | One process only | Per milestone |
Half a day of watching welders is not a qualification audit. Re-reading a business licence for a fourth repeat order is not a project audit either.
The 25 checks below are written for the full qualification audit. For a project audit, pull the lines that touch your material, your code and your duty — in practice numbers 6, 10, 14 and 17 — and move quickly through the rest.
The 25 checks, in six blocks

Block 1 — Quality system and licences (5 checks)
| # | Check | What to look for |
|---|---|---|
| 1 | Business licence + special equipment manufacturing licence | Class A/B pressure vessel scope; does the scope cover your equipment, and when does it expire? |
| 2 | ISO 9001 quality management system | Certificate valid and the floor matches the manual, not a framed poster |
| 3 | Product certification scope | ASME U-Stamp, PED 2014/68/EU, class society works approvals: read the scope and validity, not the logo |
| 4 | Organisation and key posts | Are quality, welding and inspection staffed by dedicated, qualified people? |
| 5 | Subcontractor list and their approvals | Heat treatment, NDE, painting — the sub's licence is your risk |
Check 2 is where bluffing shows up first. Everyone has the certificate. Pull two recent projects at random and ask for the quality records: look at signatures, dates, and the traceability of document numbers. Thirty minutes of that tells you whether the system runs or whether it is dusted off for auditors.
On check 3, be precise about what a stamp covers. In our own case, exactly: ASME U-Stamp (Section VIII Div. 1), PED 2014/68/EU and ISO 9001, plus CCS Type and Works Approval and works approval from DNV, LR, BV, NK and RINA, plus KGS for the Korean market. A good auditor makes the supplier state the list in that form — scope, division, market — and then checks the certificate against the statement. Vagueness here is a signal in itself.
Block 2 — Welding capability (4 checks)
| # | Check | What to look for |
|---|---|---|
| 6 | WPS / PQR procedure qualification | Does it cover your material and thickness combination? |
| 7 | Welder qualification (WPQ) | In date, and the qualified range matches what they are actually welding |
| 8 | Consumable control | Baking, issue and return records closed out; grades traceable |
| 9 | Welding equipment and traceability | Machines calibrated; base metal and consumable IDs reconcile |
Half the quality of a pressure vessel lives in its welds. Check 6 is the highest-yield line on the whole form, and it only works if you bring your own drawing. If the project is duplex 2205 or Inconel and the PQR file has no matching qualification, that is a hard gap. A works that is genuinely capable will hand over the PQR index and let you pick.
Block 3 — NDE and testing (4 checks)
| # | Check | What to look for |
|---|---|---|
| 10 | NDE personnel qualification | RT / UT / MT / PT Level II or above, certificates in date |
| 11 | Records and independence | RT film and UT reports properly archived; interpretation independent of production |
| 12 | Pressure and leak testing | Complete test records; gauges within calibration |
| 13 | Post-weld heat treatment | Automatic furnace charts; furnace temperature uniformity survey on file |
The tell here is retrieval speed. Ask for the RT film of a specific weld seam on a specific vessel shipped three months ago. A works with a live system produces it in ten minutes. A works with a filing cabinet full of good intentions produces it tomorrow, or never.
Block 4 — Material and traceability (3 checks)
| # | Check | What to look for |
|---|---|---|
| 14 | Incoming verification and mill certificates | Incoming re-testing; EN 10204 3.1 / 3.2 certificates complete |
| 15 | Marking transfer | Hard stamp or colour code after cutting; the ID chain never breaks |
| 16 | Offcuts and non-conforming material | Segregated, labelled, disposal recorded |
Traceability is where export orders die. At final acceptance an overseas owner takes the mill certificate out of the completion file and walks it back to a hard stamp on the steel. If any link fails to reconcile, the whole batch is in question. This block also quietly determines whether carbon data will ever be verifiable — the embedded carbon of a plate whose origin cannot be proven cannot be certified either.
Block 5 — Project execution and inspection plan (4 checks)
| # | Check | What to look for |
|---|---|---|
| 17 | ITP (Inspection and Test Plan) | Are the Hold / Witness / Review points set sensibly? |
| 18 | Dimensional and nozzle control | Nozzle orientation, flange facing, overall length controlled in-process |
| 19 | Schedule and long-lead items | Forgings and tubes requisitioned ahead of the production node |
| 20 | Completion documentation package | As-built drawings, quality records and certificates assembled at delivery, not after |
Check 19 is the one procurement should own, and the one most often skipped. The equipment can be flawless and the project still slips because the tube bundle material landed three weeks late. Asking when the order for those tubes was actually placed is worth more than reading ten certificates.
Block 6 — Compliance, carbon and ESG (5 checks, the new block)
| # | Check | What to look for |
|---|---|---|
| 21 | HSE and process safety | Safety record, emergency plans, PPE actually worn on the floor |
| 22 | Labour and employment compliance | Can they support CSDDD / LkSG supply chain due diligence? |
| 23 | Business compliance | Anti-bribery, export control, sanctions screening declarations |
| 24 | Product carbon accounting | With CBAM definitive from 2026, can they provide third-party verifiable embedded-emissions data? |
| 25 | Environmental management | ISO 14001, waste and hazardous substance controls |
This block did not exist in most audit forms two years ago. Check 24 is the sharp end. For steel pressure equipment going into the EU, the importer needs verified embedded-emissions figures from 2026 onwards. If a works cannot calculate the embedded emissions of a single vessel and produce a defensible ledger, the importer either buys CBAM certificates against default values and carries the cost, or changes supplier. Write line 24 into the vendor qualification standard now, rather than after the purchase order is signed.
What check 24 looks like in practice
Because this is the newest line, it is the one where both sides are still learning what a good answer sounds like. Concretely, a works that can support CBAM should be able to produce the following without a two-week delay:
- Installation identity. Which plant produced the goods, its address and operator. A package built across more than one shop involves more than one installation.
- Goods identified by CN code, reconciled to the same line as the emissions figure.
- Direct process emissions and indirect emissions from purchased electricity, per tonne of goods.
- Precursor data from the steel mill. For a fabricated vessel this dominates the total, and it is upstream of the fabricator.
- The calculation basis — measured data or default values, and the monitoring methodology used.
Two observations worth carrying into an audit. The largest determinant sits with the plate mill, not the fabrication shop: an electric arc furnace route on a low-carbon grid produces a materially different figure from a blast-furnace route for identical plate. And the data is slow to assemble the first time and quick on repeat orders, which means a supplier who started before being asked is simply further along, not necessarily more virtuous.
What it looks like from the other side of the table

The failure mode of most audit checklist content is that it is written by someone who has never been audited. A few concrete examples of what auditors actually focused on here:
GS E&C, MFC project. A cluster of heat exchangers to ASME and KGS requirements; the largest DN1000 and around 15.8 tonnes, materials ranging from SA516 to 304L. With that material spread the audit went straight to welding procedure coverage and material traceability — change the material on the drawing and the PQR and the mill certificate have to follow.
Air Products, Samsung project. A steam generator with an Inconel and duplex 2205 shell and SB-163 tubes, difficult materials to weld. The audit weight landed on welder qualification and NDE records.
Air Liquide Korea (intercoolers) and TGE (LNG skid packages for dual-fuel vessels). Each came with class society or KGS witnessing, so the emphasis was on ITP witness points and the completion documentation package.
How to spend the day
A qualification audit is a time budget. Spending it evenly across 25 lines is the most common way to end up with a thick report and no conclusion. A rough allocation that works:
- Documents first, on arrival, for around two hours. Certificates, PQR index, welder register, NDE personnel list, ITP samples. This determines what to look for on the floor.
- Floor walk against a live job, not a showcase. Ask to see a vessel currently in production and follow it backwards: drawing, material certificate, marking transfer, welding record.
- Two random retrieval tests. One RT film and one mill certificate, both for units already shipped. Time the retrieval.
- Close with the open questions written down, with dates. An audit that ends verbally ends nowhere.
What separates a real audit from a factory tour is not the length of the checklist. It is whether the auditor traced one real unit end to end.
Lmart holds ASME U-Stamp, PED/CE, ISO 9001 plus CCS (Type & Works Approval) and works approval from DNV, LR, BV, NK & RINA (KGS for Korea).
103-mu campus in Zhangjiagang · 38,000 m² workshop · 300+ staff · 15,000 T/year capacity
Last reviewed: 28 July 2026 · Technical accuracy verified by Lmart Engineering Dept.
Frequently Asked Questions
How long should a supplier qualification audit take?
One to two days for a full qualification audit of a new supplier. A project audit before a significant order is half a day to one day, scoped to that project's material, code and duty. A witness audit covers one operation at a Hold or Witness point.
Which check gives the most information for the time it takes?
Welding procedure qualification coverage. Bring your own drawing and ask the works to produce the PQR that covers that material and thickness combination. If the project is duplex 2205 or a nickel alloy and no matching qualification exists, that is a hard gap rather than a discussion point.
What does CBAM require from the factory in an audit?
Installation identity, goods identified by CN code, direct process emissions and indirect emissions from purchased electricity per tonne of goods, precursor data from the steel mill, and the calculation basis. For a fabricated vessel the steel mill's figure dominates the total.
How do you tell a real quality system from a framed certificate?
Retrieval speed and traceability of document numbers. Pull two recent projects at random, ask for the quality records, and check signatures, dates and numbering. Then ask for one RT film from a unit shipped months ago and see how long it takes.
Which checks matter most for a repeat order?
The project-specific lines: welding procedure coverage for this material, NDE personnel qualification, incoming material verification, and the ITP. Re-reading the business licence on a fourth repeat order adds nothing.
Ready to Discuss Your Project?
Our engineering team delivers technical proposals with GA drawings and budget pricing within 48 hours. 300+ staff, ASME U-Stamp · PED/CE · CCS + DNV/LR/BV/NK/RINA, equipment exported to 50+ countries.